SAP PP TUTORIALS-
Flexible Planning SOP Process in SAP PP(Production Planning)|S4 HANA|ECC 6.0: A Step-by-Step Guide-
Introduction-
Flexible Planning SOP Process in SAP PP(Production Planning)|S4 HANA|ECC 6.0-: Overview
In SAP HANA AND ECC 6.0 Flexible Planning in Sales & Operations Planning (SOP) allows all companies to define their own planning structures and key figures to meet specific business needs.like standard SOP, which uses predefined key figures (Example, sales quantity, production quantity etc.), Flexible Planning enables customization based on business requirements...
Follow Steps Flexible Planning (SOP) Process-
STEP1-
-1)Creation Info Structure-MC21
SAP Menu Path → SPRO → Logistics → Production → Information System → Logistics Information System (LIS) → Environment → Information Structures → Create (MC21)..
-Access Transaction MC21-
-Enter MC21 in the SAP command field and press Enter.
-Define your own planning structure (Info Structure).
-Example: S988 (Custom Info Structure),Name-Pramod_new info structure,Application-01,Tick-Plng Possible-
-Then Coose Charecter Button (CLICK)-
-Click on -IS Beverages Pendulum List-
-Then select field CatLog-e.g.-material-
-Then select copy+close Button-
-Then Select key figure-choose key figure button
-Then select-Key Figures: SOP
-Then select field CatLog-which you want e.g-sales
-SAVE and Then click on generate button-
STEP2-
-2)Activate info Structure-MC22
-Check active or not-
-if not activated then USE TCODE–MC22-
-Then select Generate Button-
STEP3-
-3)Assign Planning Parameter to info Structure-MC7F
-Select your info structure go to details button-S988
-Select Method-K, Select Plant-1254, Planning Periods-M, Factory Calender-01
STEP4-
-4)Create Planning Hierchy(Table)-MC61
*NOTE-You can only Create one planning Hierchy per info structure
-Create a planning table using your info structure-S988
-Select Sales Org-2004 Distribution Channel-24
-CLICK on next level button(maintain to material)
-Example-Select material-400080 and Maintain Division-34, Aggr fact.1, Proportion-50
-Go to Dispaly Mode-Check Hierchy Graphic
-Select Planning Hierchy-Select Dispaly
STEP5-
-5)Create Planning Types and Macros-MC8A
-CREATE OWN PLANNING TYPE-Z_PRAM_PT, AND SELECT-INFO STRUCTURE-S988
-SELECT PLANNING START-01.01.2025, FUTURE PERIOD-12, HISTORICAL PERIOD-2
-CLICK BUTTON -TICK
-CLICK ON STRUCTURE BUTTON-AUTOMATICALLY SHOES KEY FIGURE-
-AND MAINTAIN ONE BY ONE (E.G-SALES,PRODUCTION,STOCK LEVEL,TARGET STOCK LEVEL)-
-CREATING MACROS- CLICK ON MACROS BUTTON- SET MACRO DISCRIPTION-STOP_SYNC
NEXT-MAINTAIN KEY FIELDS-OPERAND-SALES,OPERAND-PRODUCTION,RESULT-PRODUCTION
SAVE-
STEP6-
-6)Calculation Proporation Factor-MC9B
-SELECT STRUCTURE-S988 AND EXECUTE
SAVE-
STEP7-
-7)Planning in the planning table-MC93
-SELECT PLANNING TYPE-Z_PRAM_PT ,SELECT NEW VERSION-002,THEN SELECT SALES-QTY EXAMPLE-JAN-1000,FEB-1500
-CLICK ON DETAILES SHOWS ALL DOWAN LEVEL MATERIAL –ALSO USE ARROW BUTTON FOR NEXT MATERIAL
-THEN SELECT MACROS-STOP_SYNC, ALSO YOU CAN MANTAIN ALL OTHER MATERIAL
SAVE-
STEP8-
-8)Copy planning version-MC8V
-SELECT-STRUCTURE-S988 THEN
-Copy from Source Version 005- (active) to Target Version A00- (simulation).
-SELECT-YES
SAVE-
STEP9-
-9)Transfer planning data to demand mangment-MC90
-Final approval and release of the planning data for execution.
-SELECT MATERIAL-21, PLANT-1254,INFO STRUCTURE-S988, VERSION-A00
-SELECT KEY FIGURE-PROD, FROM DATE-, REQUIREMENT TYPES-LSF,VERSION-00, SELECT ACTIVE-TICK
-SELECT -THEN TRANSFER NOW BUTTON-
SAVE-
STEP10-
-10)Stock/Requirement List-MD04
-SELECT MATERIAL-21, PLANT-1254,THEN EXCUTE-CHECK PLAN AVILABLE AND REQUIRMENT-
SAVE-